To carry out the full electrical installation to 93 units to the last phase.
Project Challenges:
Barratt are renowned for being fast developers so this had a very fast, short programme of six months.
Project Solution:
We liaised very closely with the client and other various subcontractor companies to form a highly efficient project team. We also employed additional resources working at accelerated hours. This included out-of-hour and weekend work.