Golding Homes

Client: Mitie

Type of work: Testing and Inspection Programme

Project Value: £1.5m

Duration: 30 weeks

Project Brief:

To carry out a full electrical testing programme on behalf of Mitie and Golding Homes, carrying out tests and remedials to over 3000 properties.

Project Challenges:

The client requested that all tests were to be carried out and completed within six months, making this a very fast programme. The scope of the project was also a challenge, covering a vast area of Maidstone and surrounding areas.

Project Solution:

We mobilised additional labour to cope with the programme which included weekend work.  We also employed extra back office staff to cope with the high volume of test certificates and admin.